Successful delivery of HS2 has been rated as “unachievable” since June 2019, report shows. Today, the National Audit Office has produced a report which amongst other things concludes that “HS2 is over...
Commons Library Alters Briefing to Prove £65bn HS2 Cost Estimate Came From Government. A briefing paper written for the House of Commons Library has been edited following accusations from the Department...
HS2 Property Cost Forecast at Five Times the Original Estimate, FOI Shows A Freedom of Information Response from HS2 Ltd forecasts that the final total for the cost of land and...
HS2 Ltd Threaten More Jobs, Continuing to Seize Businesses Without Paying for Them It is a shining endorsement of how well the Brexit Firewall has kept almost everything else out of the...
Behind the Brexit Firewall, HS2 has been Trundling on at Panic Stations with Increased Costs, Incompetence, Spin and Fraud. With the Brexit Firewall incinerating almost everything else that has the audacity to try and become news, you might...
HS2 Ltd Chose Most Destructive and Cheapest Option for Phase 2b. The Stop HS2 campaign has decried the route proposed for Phase 2b of HS2 is the “Most destructive and...
National Audit Office report shows HS2 property cost estimate has trebled. Today, the National Audit Office has published a report into HS2 buying land and property on...
HS2 in Parliament Twice This Week, With More to Come. This week, HS2 is due to come up in Parliament twice. On Wednesday, Stone MP Bill Cash has organised...
Minister locked in farm by campaigner refuses to accept complaint from HS2 Ltd whistleblower. Today (Monday 25th June), HS2 Minister Nus Ghani found was locked into a farm in Kenilworth at the...
Whistleblower Claims HS2 “Knowingly Misled Parliament” Covering Up £1.9bn “Petrifying Overspend” Doug Thornton, the former head of property at HS2 Ltd has told The Sunday Times that...